Permaban AlphaJoint Installation Guide
Using AlphaFeet Method
Installation Guide Issue V1.0
05/10/21
06 Vibrate Concrete
Poker vibrate along length of the joint to compact the concrete.
Poker
Wet concrete
07 Finish
Finish concrete, flush to top of the armoured joint ensuring the rail is clearly viable.
All content found within this installation guide is approximate. RCR Flooring Products Ltd reserves the right to amend
this installation guide at any time. For further details, please contact RCR Flooring Products Ltd.
RCR Flooring Products Ltd is registered in England & Wales - No. 02815314.