Checklist for commissioning

Table B- 1
Checklist
No.
Work step
1
Check installation location
1.1
Check sufficient lighting
1.2
Check minimum clearances:
front: 0.80 m
side: 1 m
rear: 1 m
top: 0.20 m
2
Prepare & check the base area
2.1
Base area level?
2.2
Base area dry?
2.3
Carrying capacity sufficient for overall weight of the charging station?
2.4
Position of the power supply cable gland suitable? (from front: front left)
2.5
Position of the DC cable gland suitable? (from front: rear left)
2.6
Check dimensional accuracy of fastening points
Distances at sides: 451.5 mm
Distances front and rear: 654 mm height bolt anchor: 50 mm
2.7
Check sufficient recesses for power cable entry
2.8
Minimum clearance 0.25 m for laying communication, control and auxiliary cables to power
cables possible?
2.9
For TT system only: Install deep grounding
3
Prepare cables
Check that cables are disconnected from the power
3.1
Lay the power cable
3.2
If present: Lay the Ethernet cable
3.3
If dispenser: Lay the DC cable
3.4
If dispenser: Lay communication, control and auxiliary cables with 0.25 m minimum clearance
to power cables
3.5
Cut cables and wires to length
3.6
Remove cable sheath
3.7
Protect cables and wires from environmental influences
4
Goods acceptance
4.1
Check the transport packaging
4.2
Check the shock indicator
Present
Intact
Serial number
4.3
Check completeness and correctness of the delivery
102
Operating Instructions, 02/2021, 8EM5907-0AA00-1AA7.01
B
Done