4 Commissioning / 4.3 Commissioning after taking out of operation
4.3

Commissioning after taking out of operation

If present
Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
u
gas outlet.
Remove the locking screws on the water connections and fit the water pipe.
u
General
Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
u
ter residues and clean it. Remove any foreign objects that may be present.
Check and clean filter silencer or air supply line, and remove any foreign objects that may
u
be present.
Put engine-side oil circulation to the turbocharger into operation.
u
Prepare the turbocharger for operation (see
u
The turbocharger is now ready for operation.
u
© Copyright 2021 ABB. All rights reserved.
Checks before commissioning
HZTL4037_EN
→35).
Rev.G
June 2021