4.2.1
Introduction
Inspection procedures include preventative visual controls, monitoring and measuring work
before and during commissioning. Inspection procedures enable changes to the turbochar-
ger to be detected. Machine damage can be prevented.
4.2.2
Checks before commissioning
Filter mat (if available)
Check for damage and contamination.
u
Lubricating system
CAUTION
Contaminated oil
Serious damage to engine or property can be caused by dirt and solid ma-
terial particles in the oil.
For the initial commissioning phase and after all service work, flush the
u
complete lubricating system with warm oil.
Use special running-in filters when running in the engine and after all ser-
u
vice work on the lubricating system.
Check that the oil filter is clean before commissioning.
u
Adhere to lubricating oil pressure at the inlet.
u
Adhere to lubricating oil temperature at the inlet.
u
For permissible values, see chapter
u
Warning plates
Check whether warning plates are present and legible.
u
Check whether the protective sheets have been removed.
u
© Copyright 2021 ABB. All rights reserved.
Monitoring operation
HZTL4037_EN
→38.
Rev.G
June 2021

Advertisement

Table of Contents
loading

This manual is also suitable for:

12453730

Table of Contents