PEWA Megger PCITS600/2 User Manual

Primary current injection test sets

Advertisement

Available languages

Available languages

Quick Links

M
PCITS600/2 & PCITS2000/2
Primary Current Injection
Test Sets
User Guide
Benutzerhandbuch

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Megger PCITS600/2 and is the answer not in the manual?

Questions and answers

Summary of Contents for PEWA Megger PCITS600/2

  • Page 1 PCITS600/2 & PCITS2000/2 Primary Current Injection Test Sets User Guide Benutzerhandbuch...
  • Page 2: Safety Warnings

    SAFETY WARNINGS • The Test Set must be properly earthed before use. • The output terminals must be clean and free of grease and dirt before switching on. • The output test leads must be of the correct rating. • The Test Set must be switched Off by the power switch before any connections on the set or the equipment under test is touched.
  • Page 3: Table Of Contents

    Contents Safety Warnings General Description Applications Specification Accessories Operation Warnings Precautions Preliminary procedure Setting the display options Current injection and IDMT testing Manual testing IDMT Forward test IDMT Runback test IDMT Dual test Auxiliary voltage testing Other messages Guidance in Choice of Test Leads for Current Carrying Capacity Duration Tests Circuit Description Sicherheitshinweise...
  • Page 4: General Description

    General Description The PCITS600/2 and PCITS2000/2 Primary Current Injection Test Sets are rugged, self-contained instruments designed for operation by one person. They provide facilities for testing all elements of electricity supply/distribution protective equipment. The PCITS600/2 is built into a tough moulded plastic casing, with carrying handles, and has a protective cover over the terminal panel.
  • Page 5: Figure 1 Pcits600/2 And Pcits2000/2

    Figure 1 PCITS600/2 and PCITS2000/2...
  • Page 6 General Description results appear on the display screen. Three tactile membrane key switches on the controller are used to operate the test set. Each key is allocated more than one function during the test procedure, and these functions are indicated on the display at the relevant point in the programme. Time Counter (IDMT Testing) Each test set has a built-in time counter for measuring the time the relay under test takes to operate, or to reset itself.
  • Page 7: Applications

    Applications Applications The main application of these Primary Current Injection Test Sets is the testing of complete electrical distribution/supply relay protection systems. They are normally employed at the time of commissioning protection equipment or after major repair since it is usually inconvenient to take the complete system “off line”.
  • Page 8: Specification

    Specification Maximum Current Output a.c. PCITS2000/2 2000 A at 0 to 3 V, 50 Hz/60 Hz 1000 A at 0 to 6 V, 50 Hz/60 Hz PCITS600/2 600 A at 0 to 4 V, 50 Hz/60 Hz 300 A at 0 to 8 V, 50 Hz/60 Hz Auxiliary Voltage Output a.c.
  • Page 9: Accessories

    Accessories Optional extras Part Number 2000 A low inductance lead set (3 m long) 6220-462 600 A low inductance lead set (5 m long) 6220-463 (Duty cycle on test leads, 2 ⁄ minutes on and 15 minutes off) Trolley for PCITS600/2 6320-224 Leads for timer stop and auxiliary voltage outputs 6131-340...
  • Page 10: Operation

    Operation Warnings 1. The test set is only to be used by a suitably trained and competent person who is familiar with current injection testing and who is aware of the hazards involved in working with heavy current equipment. 2. Ensure that the test set is properly earthed before use, either through the mains supply cable or through the separate green/yellow wing-nut terminal on the terminal panel.
  • Page 11: Preliminary Procedure

    Preliminary Procedure 1. Isolate the protection equipment to be tested. Ensure that the test set is disconnected from the mains supply before making (or breaking) connections. 2. Connect the test cables to the test set and to the equipment under test. For current injection and IDMT relay testing connect heavy current test cables to the wing-nut current terminals.
  • Page 12: Setting The Display Options

    Operation Setting the Display Options 1. From the main menu display screen press the right hand key labelled ‘DISP’. The ‘DISPLAY OPTIONS’ sub-menu appears. The keys are labelled ‘CONTRAST’, ‘LANG’ and ‘MENU’. Pressing the ‘MENU’ key returns to the main menu as shown in figure 4. 2.
  • Page 13: Manual Testing

    3. Manual testing From the ‘CURRENT’ testing options screen press ‘MANUAL’. Preset the required test current using ‘up-arrow ‘or ‘down-arrow’ keys. MANUAL IDMT MENU SET CURRENT: xxA Press ‘START’ to begin a test START xxxA Use arrow keys to increase or decrease the ‘SET CURRENT’...
  • Page 14: Idmt Forward Test

    Operation 4. IDMT testing a) Forward test From the ‘CURRENT’ testing options screen press ‘IDMT’, then’ FWD’. MANUAL IDMT MENU IDMT: SELECT TEST RUNBACK DUAL IDMT: FORWARD SET CURRENT: xxxA Use arrow keys to increase or decrease SELECT the ‘SET CURRENT’ Return to the current testing SET CURRENT: xxxA...
  • Page 15: Idmt Runback Test

    b) Runback test From the ‘CURRENT’ testing options screen press ‘IDMT’,then ‘RUNBACK’. MANUAL IDMT MENU IDMT: SELECT TEST RUNBACK DUAL IDMT: RUNBACK SET CURRENT: xxxA Use arrow keys to increase or SELECT decrease the ‘SET CURRENT’ Return to the current testing SET CURRENT: xxxA option screen RETURN...
  • Page 16: Idmt Dual Test

    Operation c) Dual test From the ‘CURRENT’ testing options screen press ‘IDMT’, then ‘DUAL’. This is a combined forward and runback test. MANUAL IDMT MENU IDMT: SELECT TEST RUNBACK DUAL IDMT: DUAL SET CURRENT: xxxA Use arrow keys to increase or decrease SELECT the ‘SET CURRENT’...
  • Page 17: Auxiliary Voltage Testing

    Auxiliary Voltage Testing 1. From the main menu press the key labelled ‘V’ (with the range selected). The options ‘MANUAL’ and ‘MENU’ are given from the ‘AUX VOLTS’ options screen. (Press ‘MENU’ to return to the main menu). AUX VOLTS: 0-250V MANUAL MENU Figure 6 The ‘AUX VOLTS’...
  • Page 18: Other Messages

    Operation Other Messages During operation events might occur which prohibit the normal operation of the test set. When this happens the display screen will show ‘SYSTEM ERROR’ and a message to indicate what is causing the the malfunction A brief Summary of these messages is given below. ‘THERMAL OVERLOAD’...
  • Page 19: Guidance In Choice Of Test Leads For Current Carrying Capacity

    Guidance in Choice of Test Leads for Current Carrying Capacity The impedance of any lead set used to connect the Test Set to the load directly affects the maximum current that can be achieved. Given that impedance comprises both resistance and reactance, it is important that both these parameters are kept to a minimum to allow the higher currents to be achieved.
  • Page 20: Duration Tests

    Operation Duration Tests The graph below gives a guide to the maximum duration of a single test at a specified output current, at 20˚C ambient. Recovery time after a full duration test is 15 minutes; operation is continuous at approximately 40% of full power.
  • Page 21: Circuit Description

    Circuit Description The PCITS600/2 and PCITS2000/2 are mainly intended for use in testing protection relays in electricity supply installations. Other general uses include current transformer testing. Each test set provides a variable high current source and an auxiliary voltage source. Both outputs can be pre-set before a test and remain stable under varying load conditions or varying supply voltages during operation.
  • Page 22 Circuit Description Solid State Relay Drive A solid state relay is used to switch the mains supply to the primary of the variac. The secondary cannot be switched because the secondary voltage falls below the 28 V required to turn on the back to back SCRs in the relay.
  • Page 24: Sicherheitshinweise

    SICHERHEITSHINWEISE • Das Prüfgerät muß vor Gebrauch ordnungsgemäß geerdet werden. • Die Ausgangsanschlüsse müssen vor dem Anschalten sauber und frei von Fett und Schmutz sein. • Es muß die richtige Klasse von Ausgangsprüfkabeln verwendet werden. • Vor dem Berühren der Anschlüsse des Prüfgerätes oder irgendwelcher Teile des geprüften Gerätes muß...
  • Page 25: Betriebsanleitung

    Betrieb Sicherheitshinweise 1. Dieses Prüfgerät dauf nur von einer geschulten und sachkundigen Person in Betrieb genommen werden, der die modernen Methoden der Injektionsprüfung und die Gefahren bei der Arbeit mit Starkstromausrüstung bekannt sind. 2. Vor Benutzung sicherstellen, daß das Prüfgerät richtig geerdet ist. Die Erdung kann entweder über das Netzkabel erfolgen oder über den separaten grün-gelben Flügelmutteranschluß...
  • Page 26 Betrieb Vorbereitung 1. Schutzausrüstung, die geprüft werden soll, isolieren. Vor dem Vornehmen (oder Unterbrechen) von Anschlüssen sicherstellen, daß das Prüfgerät nicht an den Netzstrom angeschlossen ist. 2. Prüfkabel am Prüfgerät und an der zu prüfenden Ausrüstung anschließen. Zur Strominjektion und zur Prüfung von IDMT-Relais Starkstromkabel an die Flügelmutterklemmen anschließen.
  • Page 27 Einstellung der Bildschirmanzeige 1. Drücken Sie im Bildschirm des Hauptmenüs die mit "ANZ" gekennzeichnete rechte Taste. Es erscheint das Untermenü "ANZEIGEOPTIONEN”. Die Tasten sind mit "KONTRAST“, "SPRACHE“ und "MENÜ" gekennzeichnet. Durch Drücken der Taste "MENÜ" können Sie zu dem in Abbildung 4 gezeigten Hauptmenü...
  • Page 28 Betrieb Manuelle Prüfung Drücken Sie im Prüfoptionsbildschirm "STROM" auf "MANUEL". Der gewünschte Prüfstrom wird über die Aufwärts- und Abwärtspfeiltasten gewählt. Nach Drücken von "START" wird die Prüfung automatisch begonnen und der Strom bis zum eingestellten Stand erhöht. Dieser Stand wird beibehalten, bis die Taste "EIN" gedrückt wird (womit zum Stromprüfungs- Optionsbildschirm zurückgekehrt wird).
  • Page 29 Header 4. IDMT-Prüfung a) Vorwärtsprüfung Wählen Sie im Prüfoptionsbildschirm "STROM" zunächst "RELAIS" und anschließend “VORL“. Die Betriebszeit wird auf dem Bildschirm dargestellt. Die Prüfung wird unter einer der folgenden Bedingungen beendet:...
  • Page 30 Header Rücklaufprüfung Wählen Sie im "STROM"-Prüfoptionsbildschirm "RELAIS" und anschließend "RÜCKLAUF". Die Rücklaufprüfung wird auf eine der folgenden Weisen in Gang gesetzt: (i) Abschalten des Stroms (ii) Betätigung der Relaiskontakte (iii) Drücken der START RÜCKLAUF -Taste oder (iv) nach 600 Sekunden mit laufendem Strom.
  • Page 31 Header Doppelte Prüfung Wählen Sie im Prüfoptionsbildschirm "STROM" zunächst "RELAIS" und anschließend "BEIDE". Hierbei handelt es sich um eine kombinierte Vorwärts- und Rücklaufprüfung. Die Rücklaufprüfung wird auf eine der folgenden Weisen in Gang gesetzt: (i) Abschalten des Stroms (ii) Betätigung der Relaiskontakte (iii) Drücken der “START RÜCKLAUF“ -Taste oder (iv) nach 600 Sekunden mit laufendem Strom.
  • Page 32 Betrieb Prüfen der Hilfsspannung 1. Drücken Sie (nach Wählen des Bereiches) im Hauptmenü die mit "V" gekennzeichnete Taste. Es erscheint der "HILFSSPANNUNG"-Bildschirm mit den Optionen "MANUEL" und "MENU". (Mit "MENÜ" kehren Sie zum Hauptmenü zurück.) Abbildung 6. Prüfoptionen-Bildschirm "HILFSSPANNUNG" Hinweis: Bis zu diesem Schritt des Verfahrens läßt sich der gewählte Bereich über den Schalter "BEREICH"...
  • Page 33 Betrieb Weitere Meldungen Wenn der normale Betrieb des Prüfgerätes gestört wird, erscheint auf dem Bildschirm die Meldung "SYSTEMFEHLER" zusammen mit einer Meldung, die auf die Ursache der Störung hinweist. Die Bedeutung dieser Meldungen wird im Folgenden kurz zusammengefaßt. "THERMISCHE ÜBERLAST" Diese Meldung erscheint, wenn die zulässige Betriebsdauer eines Durchgangs überschritten wurde und der Wärmeschutzschalter des Gerätes sich daraufhin abschaltet.
  • Page 34 Betrieb Hinweise zur Auswahl von Prüfkabeln mit geeigneter Stromstärke Von der Impedanz des Prüfkabels, über welches das Prüfgerät mit der Ladung verbunden wird, hängt es ab, welche Stromstärke sich maximal einstellen läßt. Da sich die Impedanz aus dem Widerstand und der Reaktanz zusammensetzt, müssen beide Parameter so niedrig wie möglich gehalten werden, um möglichst hohe Stromstärken erzielen zu können.
  • Page 35 Dauerprüfungen In der untenstehenden Kurve wird die Höchstdauer einer einzelnen Prüfung bei einer bestimmten Ausgangsstromstärke und einer Umgebungstemperatur von 20 °C dargestellt. Die Erholungszeit nach einer vollen Testlänge beträgt 15 Minuten; ein kontinuierlicher Betrieb ist bei ca. 40 % der vollen Leistung möglich. Abbildung 7b.
  • Page 36: Repair And Warranty

    Reparaturen und Garantie Das Instrument enthält statisch empfindliche Bauteile, weshalb die gedruckte Schaltung sorgfältig behandelt werden muß. Falls die Schutzvorrichtungen eines Instruments beschädigt worden sind, sollte es nicht verwendet, sondern an eine geeignete Reparaturwerkstatt geschickt werden. Die Schutzvorrichtungen sind wahrscheinlich beschädigt, wenn folgende Bedingungen vorliegen: sichtbare Beschädigung, fehlende Anzeige der erwarteten Meßergebnisse;...