Commissioning After Taking Out Of Operation - ABB HT571908 Operation Manual

Table of Contents

Advertisement

3.3
3.3
If provided
© Copyright 2016 ABB. All rights reserved.
Start-up
Commissioning after taking out of
operation

Commissioning after taking out of operation

Remove cover plates (blind flanges) between compressor casing out-
τ
let and charge air duct, before gas inlet and after gas outlet.
Inspect exhaust gas duct / line in front of and after turbine for any
τ
combustion deposits, foreign matter or residual water. Clean and re-
move.
Inspect air supply line or filter silencer for any foreign matter. Clean
τ
and remove.
Start up turbocharger oil circulation system at engine end.
τ
Prepare turbocharger for operation as instructed in section "Inspection
τ
work before start-up / commissioning" of chapter headed "Start-up /
commissioning".
Start up turbocharger.
τ
Operation Manual / TPS44-F.. - TPS61-F..
3
3.3
Page 41