Inspection work

Inspection work
Inspection work includes preventive visual controls plus monitoring and
measuring work before and during commissioning. Inspections help detect
changes to the turbocharger. Machine damage can be avoided.
Inspection before commissioning
Check for correct functioning.
Inspect for damage.
Check oil filter for cleanliness before commissioning.
Contaminated oil
Particles of dirt and solid matter in the oil can cause serious damage to
the machine or property.
During initial commissioning and after all service work, the complete
lubricating system must be flushed thoroughly with warm oil.
When running in the engine and after all service work on the
lubricating system, special running-in filters must be used.
Check the oil pressure in the oil supply lines.
Prelubrication
Serious machine or property damage might result if the turbocharger is
not supplied with oil when the engine is starting.
Activate prelubrication device before starting engine.
Operation Manual / TPS44-F.. - TPS61-F..