Table 43: Tightening Torque (51007) - ABB HT599244 Operation Manual

Table of Contents

Advertisement

Operation Manual / 4 Product description / A150-M58/68
9 Dismantling and fitting with removed air inlet and gas outlet / 9.12
Installing the cartridge group
Fig. 59: Installing the cartridge group
Product
Size
Tightening torque [Nm]
A150-M58/68
M16
175
Table 43: Tightening torque (51007)
8. Coat the threads of the studs (51006) with high-temperature grease.
9. Align casing position of cartridge group with marking and lower into the turbine casing.
10. Remove lifting gear cross-piece of service support.
11. Install the fastening strips (51002) with Verbus Ripp® washers (51003) and hexagon
nuts (51007). Observe the tightening torque.
© Copyright 2020 ABB. All rights reserved.
HZTL4041_EN
Rev.D
March 2020

Advertisement

Table of Contents
loading

This manual is also suitable for:

A150-m68

Table of Contents