Astronergy CHSM6610M Installation Manual

Astronergy CHSM6610M Installation Manual

Crystalline silicon pv
Hide thumbs Also See for CHSM6610M:

Advertisement

Quick Links

Crystalline Silicon PV
Module Installation
Manual
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CHSM6610M and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Astronergy CHSM6610M

  • Page 1 Crystalline Silicon PV Module Installation Manual...
  • Page 2: Table Of Contents

    Catalogue Introduction ............................... 3 1.1 Purpose ................................3 1.2 Scope of liability ............................... 3 Regulations ................................. 3 Safety Precautions ............................. 3 3.1 General safety ..............................4 3.2 Operation safety measures ..........................5 Handling and unpacking ..........................6 4.1 Transport ................................6 4.2 Unpack ................................
  • Page 3: Introduction

    DC/AC applications. Please contact local connection, and maintenance of following PV modules authorities for detailed governing regulations. manufactured by Chint Solar: CHSM6610M CHSM6610M(BL) CHSM6610M/HV Safety Precautions CHSM60M-HC CHSM60M(BL)-HC CHSM6610P  Chint Solar’s modules are designed to meet the requirements of IEC61215 and IEC61730, and they...
  • Page 4: General Safety

     It is forbidden to plug in connectors of different installing, wiring, handling, and/or maintaining PV modules. modules generate direct current types and models. electricity when they are exposed to sunlight or other  It is forbidden to expose PV modules to the light sources.
  • Page 5: Operation Safety Measures

    shaded module may rise due to hot spot effect, please wear a seat belt. burning the module and causing fire hazard in  When operating PV modules in the sun, please use severe cases. insulated tools, and wear rubber gloves and ...
  • Page 6: Handling And Unpacking

    there is a load. the product packaging. The goods should be stored in a dark, dry and ventilated place. If the PV  It is strictly forbidden to try to disassemble the PV modules stored uncontrollable module, and it is strictly prohibited to remove the environment, the storage time must be less than 3 nameplate of the PV module or other parts on the months when the outer packaging of the PV...
  • Page 7: Unpack

    When the PV modules are stacked, they must be neatly the distance between the upper surface of the forklift tines and the ground should be less than 80mm, and stably stacked on a horizontal surface, and stacked otherwise collisions may easily occur, which may with the glass side facing down and the back side damage PV modules.
  • Page 8: Tilt Angle Selection

    modules: -40 °C to 85°C.  Mechanical load on PV modules: under standard installation conditions, maximum tested snow/wind load is 5400 Pa/2400 Pa and the design load (considering a safety factor of 1.5 times) is 3600 Pa/1600 Pa. Refer to 5.3 for detailed Fig.
  • Page 9: Bolted Mounting

     The PV module must be securely fastened to the mounting system. If the PV module is mounted in a snowy area, the height of the mounting system should be designed in a way that the lowest end of the PV module is not covered by snow. In addition, it should be ensured that the lowest end of the PV module is not shaded by surrounding trees or other Fig 3.
  • Page 10: Clamped Mounting

    Fig. 7 Diagram of the bolt installation process Fig. 8 Rails overlapping the long-side frame Place the PV module on top of the rack. ① Insert 4 stainless steel bolts in corresponding ② mounting holes. The 9x14mm mounting holes match with M8 bolts, while the 7x10mm mounting holes match with M6 bolts.
  • Page 11 the glass and should not deform the frame, otherwise they may cause module damage. Be sure to avoid shadowing effects from the ② module clamps. Weep holes on the module frame must not be closed or obscured by the clamps. The clamp must have at least 8mm but no more than 11mm overlap with the frame of the module (The Fig.
  • Page 12 Module type Fig 2 & Fig 3 dimension Fig 5 Fig 8 Fig 9 Fig 6 L*W*H (mm) & Fig 4 +5400/-2400Pa +2400/-2400Pa 1648*990*35 +5400Pa CHSM6610M Installation scope Installation scope 1648*990*40 -2400Pa CHSM6610M/HV 198~408mm 50~200mm CHSM6610P CHSM6610P/HV +5400/-2400Pa +2400/-2400Pa 1650*992*35...
  • Page 13 Table 1 (continue) Installation method Dimensions Module type Fig 2 & Fig 3 L*W*H (mm) Fig 5 Fig 8 Fig 9 Fig 6 & Fig 4 +5400/-2400Pa +1800/-1800Pa CHSM60M-HC +5400Pa Installation scope Installation scope CHSM60M(BL)-HC 1755*1038*30 -2400Pa CHSM60M/LV-HC 350±50mm 200±50mm +1400/-1400Pa +5400/-2400Pa CHSM54M-HC...
  • Page 14: Electrical Installation

    Where: Electrical Installation N: number of PV modules in a single string Electrical characteristics : open-circuit voltage of each PV module (refer to The electrical characteristics are detailed in the PV the PV module nameplate or product manual) module product manual. : temperature coefficient of PV module for The rated values of electrical characteristics, including open-circuit voltage (refer to the PV module product...
  • Page 15: Electrical Connection

     Depending on the maximum rated fuse current of the PV module and the local electrical installation standards, the connection of parallel strings of PV modules needs to be equipped with suitable fuses or preventive diodes for circuit protection purposes. 6.2 Electrical connection To ensure the normal operation of the system, make sure the polarity of cables is correct when connecting...
  • Page 16: Grounding

    The PV modules are designed with an anodised, module. Do not press the cable hard. To secure the cable to the rack in the proper way, specially corrosion-resistant aluminum alloy frame as a rigid designed UV-resistant coils and cable clips must be support.
  • Page 17: Maintenance

     Insert the bolt through the cut washer and then for damages, such as glass breakage, cable breakage, through the hole in the aluminum frame. junction box damage, cell cracks, and backsheet breakage and other factors that cause functional and ...
  • Page 18: Modified Version And Date

    Modified version and date · Rev 1.0, released in June 2018. · Rev 1.1, released in July 2020. · Rev 1.2, released in October 2021. CHINT SOLAR (ZHEJIANG) Co., Ltd. Add: 1335 Bin’an Rd, Binjiang District, Hangzhou, China 310053 Tel: 86-571-5603 1888 Fax: 86-571-5603 2333 http://energy.chint.com/...