Step 5 Tap Yes. The screen for component commissioning is displayed, as shown in
Figure
Figure 4-24 Fan commissioning
Step 6 View the commissioning result.
●
●
Issue 07 (2021-12-30)
NO TE
● If the system is not configured with the electric heater and humidifier components, the
electric heater and humidifier commissioning items will not appear on the screen.
● If the heating function and humidification function are disabled, you cannot select the
electric heater and humidifier items.
● All the items are selected by default if you first enter the screen where you select
commissioning items. Except that the indoor fan item is mandatory, you can clear other
commissioning items that are not required.
4-24.
NO TE
The fan commissioning item is mandatory. After commissioning for a component succeeds,
the system automatically performs commissioning for the next component you selected. If
commissioning fails, startup wizard ends.
The screen shown in
succeeds.
Figure 4-25 Commissioning successfully
The screen shown in
fails, which ends startup wizard commissioning.
Copyright © Huawei Technologies Co., Ltd.
Figure 4-25
is displayed if component commissioning
Figure 4-26
is displayed if component commissioning
4 Power-On Commissioning
124