4.
Check that EAFALM and ERFALM are low.
5.
Increase the supply currents or voltage in next 1 minute cycle such that the active or reactive
energy values are greater than the EALim and ERLim setting default values respectively.
6.
Check that EAFALM and ERFALM are high after 1 minute.
7.
Similarly the testing can be done for EARALM and ERRALM outputs by changing the power
inputs directions through direction settings.
9.10.2.2

Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore
connections and settings to the original values, if changed for testing purposes.
9.11

Station communication

9.11.1
Multiple command and transmit MULTICMDRCV /
MULTICMDSND
The multiple command and transmit function (MULTICMDRCV / MULTICMDSND) is only applicable
for horizontal communication.
Test of the multiple command function block and multiple transmit is recommended to be performed
in a system, that is, either in a complete delivery system as an acceptance test (FAT/SAT) or as parts
of that system, because the command function blocks are connected in a delivery-specific way
between bays and the station level and transmit.
Command and transmit function blocks included in the operation of different built-in functions must
be tested at the same time as their corresponding functions.
9.12

Basic IED functions

9.12.1

Parameter setting group handling SETGRPS

Prepare the IED for verification of settings as outlined in section
9.12.1.1

Verifying the settings

1.
Check the configuration of binary inputs that control the selection of the active setting group.
2.
Browse to the ActiveGroup menu to achieve information about the active setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test /Function status/
Setting groups /ActiveGroup
The ActiveGroup menu is located on the PCM600 under Main menu/Test/Function status/
Setting groups /ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary input of the IED and observe
the information presented on the local HMI.
The displayed information must always correspond to the activated input.
4.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups are
described in the corresponding PCM600 documents and instructions for the operators within
the SCS are included in the SCS documentation.
Busbar protection REB650
Commissioning manual
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Testing functionality by secondary injection
"Preparing for test"
in this chapter.
Section 9
M13906-301 v5
SEMOD53595-1 v1
SEMOD172432-5 v3
SEMOD52026-1 v1
M11369-2 v4
M11369-4 v5
85

Advertisement

Table of Contents
loading

This manual is also suitable for:

Reb650Relion 650Relion reb650

Table of Contents