Commissioning, inspection, maintenance
Steps - commissioning, inspection and maintenance
Commissioning steps
Inspection steps
Maintenance steps
1. Filling the heating system................................................................................................. 26
4. Selecting the language...................................................................................................... 27
5. Setting the date.................................................................................................................. 27
6. Setting the time.................................................................................................................. 27
7. Selecting the number of buffer temperature sensors..................................................... 27
8. Selecting the type of heating water buffer cylinder........................................................ 27
9. Selecting an additional boiler........................................................................................... 28
10. Selecting the connection for heating circuits 1 to 3....................................................... 28
11. DHW connection................................................................................................................. 28
13. Selecting the solar connection......................................................................................... 28
14. Selecting the solar type..................................................................................................... 29
15. Changing the heating circuit designations...................................................................... 29
16. Diagnosis (if heating circuit extension module installed).............................................. 29
17. Checking the outputs and actuators................................................................................ 29
19. Ending commissioning...................................................................................................... 30
20. Displaying the menu structure.......................................................................................... 31
21. Matching the control unit to the heating system ........................................................... 31
22. Adjusting the heating curves............................................................................................ 31
23. Heat up................................................................................................................................ 33
24. Shutting down the system................................................................................................. 33
25. Hopper cleaning (if required)............................................................................................ 35
26. Cleaning the secondary heating surfaces....................................................................... 36
27. Cleaning the ash chamber and combustion chamber.................................................... 37
28. Checking the packing cords............................................................................................. 37
29. Checking the doors for tightness..................................................................................... 38
30. Cleaning the flue gas fan................................................................................................... 39
31. Cleaning the Lambda probe and air dampers................................................................. 40
32. Cleaning the air box and secondary air supply............................................................... 42
33. Cleaning the sensor well for flue gas temperature sensor............................................ 43
34. Checking the expansion vessel and system pressure................................................... 43
38. Test run............................................................................................................................... 44
39. Emissions test.................................................................................................................... 44
24
probe.................................................................................................... 30
2
Page

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vl2a

Table of Contents