1.0 PURPOSE
The purpose of this document is to define the necessary steps to configure the above 3PCI GTU's.
2.0 SCOPE
These instructions apply to the 460T23.00, 460T23.10, 460T23.20 and 460T41.00.
3.0 RESPONSIBILITY
It is the responsibility of the heating and regulating final test technician to follow this procedure.
4.0 DEFINITIONS
4.1
H/R Product Line
4.2
3PCI GTU – Three Phase Cosine Intercept Gate Trigger Unit
4.3
RROCT – Remote Reset Over Current Trip
References Schematic GTU - 479149.ALL 479150.ALL
Assembly GTU – 460T23.ALL, 460T41.ALL
5.0 PROCEDURE
5.1
The above GTU's are intially tested at the PC Board testing department as a
480VAC, 3∅, 50/60Hz, Standard one second ramp, RMS Voltage Regulator.
5.1.1
Refer to the proper schematic and assembly drawings
5.2
Customer Specifications
5.2.1
The GTU configuration is selected by the Customer Service order options program.
Line Voltage is selected by Customer Specifications
The line voltage is selected by a wire connection on each of 3 transformers. The wire
must be moved to the appropriate voltage tap and soldered.
Seven jumpers are used to configure the GTU to Customer Specifications. All Jumpers are
received in the "A" position from the PWBA Vendor.
Ramp Option
S
J1 – Ramp Adjustment
F
1.0 Second, J1 Pos "A"
E
4.0 Seconds J1 Pos "B" J2 - Pos "A"
S,E
J2 – Integrator Speed
F
CR
J3 – J4 (CR ) Current Regulation Gain Adj. Pos "A", Pos "B"
VR
J5 – Pos "A" (VR) Voltage Regulation
CR
Pos "B" (CR ) Current Regulation
Version 1.2 (19000325)
0.1 Second, J1 Open J2 - Pos "B"
J2 - Pos "A"
Pos "A",
Pos "B"
J3, J4 Pos "A"
J3, J4 Pos "B"
s

Addendum