INSTALLATION OF UNIT
9

Connection Drainage

Condensate drainage is provided on the unit. The connection is located at the rear. Use a 19 mm
diameter plastic tube.
To ensure correct condensate drainage,the drain line must be installed with a gradient of at least
2 % (2cm per metre) and without any upward slopes.
An elbow trap at least 50mm in in height must also be provided.
If possible, install a U bend fitted with an inspection cap.
Condensate drain connection
Where the condensate lines from several units are joined together, each individual outlet must be
fitted with an elbow trap.
After routing and connecting condensate lines, pour water into the collecting pan and check that
it drains correctly.
An auxiliary condensate pump could be installed in cases where drain lines cannot be routed at
the correct gradient.