1.
Check for damage and report promptly to the carrier any damage
found to the unit.
Note: If the unit must be transported in a horizontal position, it must
be laid on its back (marked "REAR" on carton).
Note: After unit is removed from the carton, depress the Schrader
valve, if equipped, to verify coil is pressurized. For units with
rubber plugs in both suction and liquid lines, carefully remove
the liquid line plug first. If no pressure is released, check for
leaks.
Note: Remove the shipping block from the blower compartment.