Summary of Contents for Xylem McDonnell & Miller MM-706B
Page 1
INSTRUCTION MANUAL MM-706B Replacement Switch Assembly Burner/Pump Control Burner/Pump Control – Manual Reset Proportional Control 7B-M Proportional Control – Manual Reset For Series: Pump Controller/Low Water Cut-Off Replacement Switch Electrical Ratings Models with 7B and 7B-M Switch Models with 5 and 5-M Switch Switch Ratings Pump and Burner Switch Contact Ratings Voltage...
Page 2
STEP 1 - Removal and Replacement of Contacts and Terminal Panels a. Turn power off to boiler and all controls. Allow boiler to cool to 80˚F (27˚C) and reduce the pressure to 0 psi (0 bar). CAUTION There may be more than one source of power to the boiler.
Page 3
STEP 2 - Testing – Dimensions shown are typical. – The following testing procedure is only meant to serve as a verification of proper operating sequence. a. Turn on power to boiler and pump circuits. With the boiler empty, the pump should turn on (5 or 5-M switch models) or the valve open (7B or 7B-M switch models).
Need help?
Do you have a question about the McDonnell & Miller MM-706B and is the answer not in the manual?
Questions and answers