Husqvarna Soff-Cut 150 Operator's Manual page 13

Hide thumbs Also See for Soff-Cut 150:
Table of Contents

Advertisement

Available languages

Available languages

been developed to permit the joint sawing very soon
after floor finishing, sometimes within 0 to 2 hours...if the
cut is sawn within a few hours after the final finishing,
random cracking can be controlled..."
Husqvarna has the only Ultra Early Entry dry-cutting
system (Soff-Cut) which controls random cracking
through the early timing of the cut. With the Soff-Cut
method, control joints are usually cut within 2 hours after
the finishing process.
Joint cutting should begin as soon as the concrete will
support the weight of the saw and the operator at each
joint location and before final set.
If the joints are not being cut within this time frame then
the Soff-Cut Ultra Early Entry method is not being
followed.
Before you operate the product
1. Do daily maintenance. Refer to
schedule on page 15 .
2. Make sure that the handle is in full upright position
and that the locking pin is installed.
3. Make sure that the front guide is turned to the
forward position.
4. Fill the oil tank. Refer to
for information about recommended engine oil.
5. Do a check of the oil level. Refer to
the oil level on page 21 .
To fill fuel
WARNING: Do not fill containers when you
are in a vehicle. Risk of fire. Put the
container on the ground away from your
vehicle.
CAUTION: Do not use gasoline with an
octane number less than 90 RON (87 AKI).
This can cause damage to the product.
CAUTION: Use unleaded gasoline. Do not
use unleaded gasoline with more than 10%
ethanol. Gasoline with more than 10%
ethanol cause a risk of fire and can also
cause starting and performance problems. It
can also cause damage to metal, rubber,
and plastic parts of the fuel system.
CAUTION: Do not use gasoline that
contains methanol.
CAUTION: Do not keep fuel more than 30
days in a container. Expired fuel can cause
damage to the product.
714 - 004 - 06.07.2021
Maintenance
Technical data on page 28
To do a check of
1. Remove the product from the transportation vehicle
and put it on the ground. If this is not possible, refuel
the product with a portable container and not from a
gasoline pump nozzle.
WARNING: Use only approved gasoline
containers.
2. Open the fuel tank cap slowly to release the
pressure.
3. Make sure that the nozzle touches the top edge of
the fuel tank opening until the fuel tank is full. Do not
use a nozzle lock-open device.
4. Clean the area around the fuel tank cap.
5. Tighten the fuel tank cap fully. If the fuel tank cap is
not tightened, there is a risk of fire.
6. Move the product a minimum of 3 m/10 ft from the
position where you filled the tank before a start.
To start the engine
1. Pull and hold the release lever when you tilt the
product. Push the handlebar down to set the product
in tilt position.
2. Release the lever to lock the product at tilt position.
3. Set the engine ON/OFF switch to the ON position
(I) . In the ON position, the fuel valve is also open.
13