Commissioning, inspection, maintenance
Further details regarding the individual steps
Flue gas emissions test
Coaxial boiler flue connection
Coaxial boiler flue connection bend
1. Connect the flue gas analyser to
test port A.
2. Open the gas shut-off valve. Start
the boiler.
3. Select the lower rated output.
Constant temperature control
unit:
K + d
press simultaneously:
"1" is shown.
Weather-compensated control
unit:
K + d
press simultaneously:
"Relay test" and then
"Base load" is shown.
38
(cont.)
Parallel boiler flue connection
A Flue gas
B Ventilation air
4. Check the CO
or O
2
tent. Enter actual values into the
service report.
5. Press d.
Operation with the lower rated out-
put is terminated.
and CO con-
2