Preparation Of The Steel Stand; Installation Of The Control Box; Installation Of The Operation Panel; Installation Of The Power Switch And Foot Switch - Mitsubishi Electric PLK-J3020R-SE Technical Manual

Industrial sewing machine
Table of Contents

Advertisement

3-2. Preparation of the steel stand

(1) If the steel stand is not MITSUBISHI original, please refer
to the dimensions shown on the figure at the right.
(2) When fitting the caster to the steel stand, the steel stand
has to be strong enough to withstand the weight and
vibration of the sewing machine.
(3) If the steel stand is MITSUBISHI PLK-J3020R-SE original,
assemble the steel stand with the assembling instructions
enclosed in the packing.

3-3. Installation of the control box

Install the control box with the instructions in the paragraph "[3] Installation" in the CONTROL UNIT
technical manual.

3-4. Installation of the operation panel

Connect the operation panel PLK-J-PAL with the CON G on the rear of the control box.

3-5. Installation of the power switch and foot switch

(1) Mount the power switch (No.1) with the wood screw (No.2) at the position as shown on the figure.
(2) Hook up the connector (No.3) of the power switch to the control box CON F.
(3) Attach the power plug (No.5) to the incoming electrical cable (No.4).
(4) Fix the electric cables with the staples (No.6) to prevent the cables from hanging down.
(5) Hook up the connector (No.8) of the foot switch (No.7) to the control box CON L.
(6) As for the control box connector, refer to the instructions in the paragraph "3-10.Connection of the
electric cables" in this manual.
[Notice] Power plug (No.5) is not included in accessory box.
<1>
<2>
<7>
<6>
<8>
<1>: Power switch
<2>: Wood screw
<3>
<3>: Power switch connector
<4>: Electrical cable
<5>: Power plug
<6>: Staple (six staples)
<4>
<5>
<7>: Foot switch
<8>: Foot switch connector
- 4 -

Advertisement

Table of Contents
loading

Table of Contents