ASSEMBLY & SET-UP INSTRUCTIONS

UNPACKING THE CONTAINER

WARNING! Use extreme caution unpacking this machine. Some components are very heavy and will require
additional people or mechanical handling equipment.
NOTE: All references in this manual to the left or right side and front or back of the log splitter are from the operating
position only. Exceptions, if any, will be specified.
Unpacking tools needed:
1. Wrench 8mm
2. Scissors or knife
Step 1: Use a 8mm wrench to remove the four bolts on the metal crate, put aside the crate top, then remove the
cardboard box. See FIGURE 2.
(FIGURE 2)
Cardboard box
Beam Assembly
Step 2: Remove all loose parts included in the container, e.g. operator's manual, log trays, mounting brackets, axel, and
hardware kits.
Step 3: . Remove the beam assembly on the crate bottom.
NOTE: DO NOT remove the strap securing the hydraulic hoses to the beam at this time, until you do all the assembly
procedures.
If any parts are damaged or missing, please call
assistance.
NOTE: DO NOT discard the packing materials until you have carefully inspected and satisfactorily operated the tool.
Page 10
Crate Bottom
our customer service department at 1-800-780-2677
Crate Top
Log Trays x 2 Sets
Hex Head Bolt
x 4 PCS