End Of Power775 Uepo Cable Service Procedure - IBM Power775 Service Procedure

Uepo cable service procedure
Hide thumbs Also See for Power775:
Table of Contents

Advertisement

27.
Wait 5 minutes and then perform Steps 28 & 29 to verify the original SRC does NOT reoccur and to confirm the
service procedure completed successfully.
28.
Issue an BPCH-A real-time Power/Thermal SRC read-out command to the HMC BPC-A ASM SIDE_A Service
Processor Command Line (Refer to 'Power775 BPC FSP Command Line Procedure' in Appendix A of this PDF
and ensure ASM SIDE_A is active per Step 12) by entering the following at the command prompt (IMPORTANT:
DOUBLE-CHECK THE COMMAND IS TYPED IN EXACTLY CORRECT BEFORE PRESSING ENTER
BECAUSE EVEN A SINGLE INCORRECT CHARACTER COULD RESULT IN SEVERE UNINTENDED
SYSTEM DISRUPTION!!):
bpccmd -m gi,3,s
Verify the original SRC problem is not listed in any of the
src.referenceCode fields (there may be multiple fields to check).
29.
Open a new ASM SIDE_B window and issue an BPCH-B real-time Power/Thermal SRC read-out command to the
HMC BPC-B ASM SIDE_B Service Processor Command Line (Refer to 'Power775 BPC FSP Command Line
Procedure' in Appendix A of this PDF and select SIDE_B on the Launch ASM Interface window) by entering the
following at the command prompt (IMPORTANT: DOUBLE-CHECK THE COMMAND IS TYPED IN
EXACTLY CORRECT BEFORE PRESSING ENTER BECAUSE EVEN A SINGLE INCORRECT CHARACTER
COULD RESULT IN SEVERE UNINTENDED SYSTEM DISRUPTION!!):
bpccmd -m gi,3,s
Verify the original SRC problem is not listed in any of the
src.referenceCode fields (there may be multiple fields to check).
30.
If any of the src.referenceCode fields list the original SRC that led you to perform this service procedure, then
continue with replacing the next item on the FRU call list or contact the next level of support.
31.
If the original SRC error has not reoccurred and is now cleared, then close the front door of the rack and close out
the HMC Service Focal Point problem as appropriate.
4 END OF POWER775 UEPO CABLE SERVICE
PROCEDURE
Power775 UEPO Cable Service Procedure
PN: 41U8503, EC N44172
27 of 32