Unit Inspection

After the unit is delivered at the job site:
- Verify that the nameplate data matches
the data on the sales order and bill of
lading (including electrical data).
- Verify that the power supply matches
the unit nameplate specifications.
- Inspect the unit carefully for any
shipping damage.
If any damage or material shortage is
found it must be reported immediately
to the carrier. Specify the type and
extent of the damage on the carrier's
delivery receipt before signing.
- Notify Trane do Brasil and/or the
contractor about the damages and
actions to repair the unit. Do not
attempt to repair the unit until the
damages are inspected.
Storage
If it is not possible to install the unit after
delivery, it should be stored in a safe
location, protected from the weather
and
other
damages.
equipment storage or handling will void
the equipment warranty.
6
Unit Inspection
Instructions for proper installation
Please consider the following items
required for proper installation before
placing the unit at the mounting
location:
- The mechanical room should be
provided with proper lighting for
servicing and maintenance.
- Make certain the floor or foundation
is level, solid, and sufficient to support
the unit and accessory weights. Level
or repair the floor before positioning the
unit.
- Provide the units with rubber pads or
vibration isolators.
-
Install the hydraulic components
required to drain the water from the
condensate tray.
-
Allow minimum recommended
clearances for routine maintenance
and service (see page 20).
-
The same clearances should be
observed in case of several units
together or condensing units.
Improper
-
Provide electrical installation. The
unit has electrical inputs on both sides.
- Provide enough clearance to access
piping and remove covers.
The power supply must comply with
Standard NBR 5410, as well as local
codes and/or NEC.
- The contractor should provide and
install the refrigeration piping - both for
the liquid line and the suction line - in
order to interconnect evaporator and
condensing units.
General Safety
The Trane equipment is designed for
safe and reliable operation, as long
as units are operated according to the
applicable safety rules. The system
uses electrical and mechanical parts,
as well as gas pressures, that may
injury people or damage the equipment
if safety rules are not followed.
Therefore, the installation, start-up and
maintenance of this equipment must be
performed only by qualified personnel
or personnel approved by Trane do
Brasil. Follow all safety standards
related to the task and warnings on unit
labels, and always use proper tools and
equipment.
Hazard Identification
!
WARNING!
Warnings appear at appropriate
intervals and sections throughout
this manual to warn operators
and service personnel about a
potentially hazardous situation
which MAY result in serious
injury or equipment damage if
safety rules are not met.
!
CAUTION:
Cautions appear at appropriate
intervals and sections throughout
this manual to warn operators
and service personnel about a
potentially hazardous situation
which may result in damage to
the equipment and/or
environment.
SSC-SVN001F-EN

Advertisement

Table of Contents
loading

Table of Contents