Secure the first module onto each Rail with
KB Konnect (KBK) Clamps. Use your Spacing
Diagram to locate the Clamp locations
relative to the module edge.
Click-in and secure End Clamps at array
edges first. The centre of each KB Konnect
Clamp must be placed at least 4" from the
module edge.
KBK Mid Clamps + End Blocks, or Integrated
End Clamps are installed at array edges.
Integrated End Clamps are for 40mm (1.57")
modules only.
3
Place the next module towards the upper end
of the roof, as shown in Figure 33. If there is
no module in this direction, completely install
the first module with four (4) KBK End
Clamps.
Click-in and secure KBK Mid Clamps between
modules.
The adjacent module must be in place before
completely installing the KBK Mid Clamp.
Rev.1, Sep 2019
Figure 32 – Example End Clamp Placement
Figure 33 – Mid Clamp Placement