PRELIMINARY INSTALLATION

INSTALLATION CONSIDERATIONS
Prior to installing the Series 700A/VS, be sure to take into consideration the site you have selected. Power
Conditioners produce heat and therefore require ventilation as well as accessibility. Consider these factors.
▪ Ventilation
▪ Size of the Power Conditioner
▪ Weight Load
▪ Audible Noise Requirements
▪ Remote Emergency Power Off (Repo)
▪ Monitors
▪ Options
▪ Clean Environment
CHOICE OF LOCATION
The unit has been completely inspected and extensively tested under various load conditions prior to
shipment. Care to install it at a proper location will assure long trouble-free operation.
The unit is air cooled with the air intake at the front and exhausts at the top. Therefore, it should be installed
in a clean, dry place with enough clearance to allow a free flow of air. Allow a minimum of 36" in front of
the 700A/VS for installation, operation, and maintenance. There is no clearance required on either the
left or right hand side of this enclosure. Either or both sides, as well as the rear of the enclosure, can be
set flush up against a wall. Input and output conductors should then enter/exit via the top and/or bottom
of the enclosure as indicated.
NO CLEARANCE REQUIRED
FRONT
TOP VIEW
▪ Input Source Voltage
▪ Receiving Facilities
▪ Distribution of Power
▪ Room Temperature
▪ Clearances
▪ Accessibility
▪ Excessively Long Power Runs
▪ Proper Ground Techniques