START UP

**** WARNING ****
THERE ARE DANGEROUSLY HIGH VOLTAGES PRESENT WITHIN THE ENCLOSURE OF
THE POWER SUPPLY SYSTEM. CAUTION MUST BE TAKEN WHEN WORKING WITH
THE ENCLOSURE. IT IS RECOMMENDED THAT ALL WORK BE PERFORMED BY
QUALIFIED ELECTRICAL PERSONNEL ONLY.
NOTE: INITIAL START-UP SHOULD BE PERFORMED WITH NO LOAD ON SYSTEM.
1. Re-install all panels that may have been removed during installation.
2. Make sure the input circuit breaker is in the off position.
3. Energize the primary building power.
4. Turn on the main AC input breaker.
5. Verify that the output voltage is within the specified range.
6. Verify output phase rotation is correct.
7. Turn the system off.
8. Connect the loads one at a time and repeat Step 4.