Safely Power Down The Device - Cisco ASR-920-12SZ-A Hardware Installation Manual

Aggregation services router hardware installation guide
Table of Contents

Advertisement

Configure the Device
This command saves the configuration settings that you create in the device using the configuration mode
and the setup facility. If the save action fails, you lose your configuration, and it is not available during your
next reload.

Safely Power Down the Device

This section explains how to shut down the device. We recommend that before turning off all power to the
device, you issue the reload command. Running this command ensures that, the operating system cleans up
all file systems. After the reload operation is complete, the device can be powered down safely.
To power down the device safely:
Step 1
Slip on the ESD-preventive wrist strap included in the accessory kit.
Step 2
Enter the reload command.
Step 3
Click the Enter key when prompted to confirm.
Step 4
Wait for the system bootstrap message before powering down the system:
Step 5
Remove power cables, if any, from the device:
• For power supplies with a circuit breaker switch, position the switch to the 'Off' (O) position.
• For power supplies with a standby switch, place the standby switch in the 'Standby' position.
After powering down the device, wait for a minimum of 30 seconds before powering it on again.
Cisco ASR-920-12SZ-A and Cisco ASR-920-12SZ-D Aggregation Services Router Hardware Installation Guide
Safely Power Down the Device
63