Quick connects are for one time use only. Once disconnected, the coupling cannot be re-used. Refrigerant leaks
will occur if the couplings are re-used resulting in poor system performance.
Excess line set length should never be allowed to coil in the vertical position. Excess line length should be laid flat on
its side.

Leak Testing

After all connections are complete the refrigeration system must be tested for leaks.
Failure to perform a leak test can result in unsatisfactory system performance, additional servicing and service costs,
and possible system failure.
Leak test should be performed using an electronic leak detector.
All joints and components, both factory and field installed, should be thoroughly inspected for leaks.
The system installation must be leak free!
Leak Testing "PR" model systems
Open both the liquid and suction service valves.
Ensure the solenoid valve is energized and open.
Add 50 psi refrigerant, then pressurize with dry nitrogen to the low side test pressure identified on the unit rating
label.
Allow thirty minutes for refrigerant to reach all parts of the system.
Check all joints and components with an electronic leak detector.