Advertisement

Quick Links

UPM II
INSTALLATION
AND OPERATION
MANUAL
I/O ZONE 560/583
1

Advertisement

Table of Contents
loading

Summary of Contents for Bosch FHP UPM II

  • Page 1 UPM II INSTALLATION AND OPERATION MANUAL I/O ZONE 560/583...
  • Page 2: Table Of Contents

    UNIT PROTECTION MODULE HARDWARE OPERATION IMPORTANT: This manual is for UPM board part numbers 8733 800 260. See controller label as shown in figure 1 to verify correct part number. TABLE OF CONTENTS Specifications ........................3 Unit Protection Module (UPM)................... 4 Power Random Start Up ....................
  • Page 3: Specifications

    Specifications Power: 24VAC ± 10%, 50-60Hz, 1.4 VA of standby power consumption (Single Class II 70VA or 100VA option available) Physical: Printed Circuit Board and plastic stand offs. Environmental Operating Range: -40° to 176°F (-40 °C to 80°C); 10 to 90% relative humidity, non-condensing All controls are conformal coated for environmental protection.
  • Page 4: Unit Protection Module (Upm)

    Unit Protection Module (UPM) The Unit Protection Module (UPM) as shown in figure 1, is a printed circuit board (PCB) that interfaces with the thermostat or the digital direct controller. The main purpose of this device is to protect the compressors by monitoring the different states of switches and sensors of each refrigerant circuit, this device provides time delays and protects the unit against freezing of the water and refrigerant heat exchangers as well as condensate overflow when the appropriate sensors are installed.
  • Page 5: Power Random Start Up

    The anti short cycle delay is 300sec delay Power Random Start Up on break during normal operation. This feature prevents multiple units sharing same electrical circuit or network from NOTE: starting at the same time. If the board is set to test mode through the “TEST” DIP switch the delay will be 5 seconds.
  • Page 6 High pressure protection Low pressure protection If the LP1 or LP2 switches are open upon a If the HP1 or HP2 switches are open upon a Y1 or Y2 call (Could be Y1 or Y2 or both) Y1 or Y2 call the UPM will not energize the the UPM will not energize the CC1 or CC2 respective outputs...
  • Page 7: Ground

    Ground UPM DIP SWITCH CONFIGURATION The UPM controller takes ground LOCKOUT reference from the unit chassis which is RESET connected to the controller via the C-GND ALARM CONT PULSE spade terminal. TEST DIP Switch Settings Figure 3 - DIP switch table The DIP switch is used to configure most of the available features of the UPM as follows: Selectable Alarm Mode...
  • Page 8: Brownout Protection

    If temperature drops below or remains at the Once the UPM detects a brownout condition freeze limit trip for 30 seconds, the controller its fault LED will flash seven (7) times as will shut the compressor down and enter into error code indication.
  • Page 9: Upm Sequence Of Operation (Soo) Flow Chart

    UPM Sequence of Operation (SOO) Flow Chart...
  • Page 10 601 N.W. 65 Court, Ft. Lauderdale, FL 33309. Phone: 954-776-5471 Fax: 954-776-5529 www.fhp-mfg.com 6 720 220 322 REV. 6-11...