Installation sequence
-
Push the inlet connector onto the valve block (figure 1)
-
Screw the valve block into the water inlet (figure 2)
-
Insert siphon trap into the outlet (figure 3)
-
Plug in the main connections (4a). The LED flashes.
-
Attach the GLT - adapter to the wall (figure 4b)
-
Secure the control unit onto the valve block (figure 5A)
-
Connect the control unit to the siphon trap (5B), to the solenoid valve (5D) and to the
GLT - unit (5C)
-
Connect the GLT - unit to the building master control system
-
Check multi-function display
-
Turn on the water. Do not darken the room.
-
Install the urinal to cover the daylight sensor (figure 7)
-
Three minutes later there will be a flush of approx. 10 seconds so that the siphon trap is filled
with water
-
After a break of 8 seconds there will be another flush of approx. 2 seconds
-
Check the GLT - unit from the control room
-
The urinal can then be used
Fault
No flush
Flush, low
Flush, constant
Flushing every 60 sec. Stadium mode
Residual water does
not flow off
Cause
Water supply interrupted
Flow limiter blocked*
Solenoid valve damaged
Cable connections interrupted
Power supply interrupted
Cleaning session
Flushstop activated by GLT
Water supply reduced
Flow limiter blocked*
Solenoid valve damaged
Low water pressure
Solenoid valve damaged
Siphon trap or drains blocked
Solution
Open shut-off or preliminary shut
-off device
Clean*
Replace valve block
Establish connections
Ensure power supply
Automatically latest after 30
minutes
Flushstop deactivate by GLT
Open shut-off or preliminary shut-
off device
Clean*
Replace valve block
Flush volume increase (page 11.1)
Replace valve block
Automatic switchover
Replace or rectify