Recent Machining Report

(1) Recent machining report is displayed.(up to 16 main programs)
Machining report for the program currently selected
• MAIN PROGRAM
The file name of the main program having been selected
• START DAY
Date of the main program selection [year/month/day]
• START TIME
Time of the main program selection [hour:minute:second]
• NO. OF WORK
The number of times the M02 or M30 command has been executed
Execution of the M02 or M30 command in the machine lock mode operation and dry run
mode operation (NC lathe) is not counted.
• OPERATING %
Percentage of machine operating time in reference to power ON time [%]
(Operating % = Machine operating time (OPERATING) / Power ON time (RUNNING) X 100)
• RUNNING
Length of time for which power supply to the NC has been ON [hours:minutes:seconds]
(Length of time for which main program has been selected)
• OPERATING
Length of time for which a main program has been executed [hours:minutes:seconds]
• CUTTING
Length of time for which an axis has been moved at a cutting feedrate [hours:minutes:sec-
onds]
Length of time an axis has been moved at a cutting feedrate in the machine lock mode or dry
run mode (NC lathe) is not counted.
• CYCLE TIME
Length of time for which power has been ON for producing one piece of workpiece
[hours:minutes:seconds/pc.]
(Cycle time = Power on time (RUNNING) / No. of workpieces (NO. OF WORK))
• MACHINING
Length of operating time used for producing one piece of workpiece [hours:minutes:sec-
onds/pc.]
(Machining time = Operating time (RUNNING) / No. of workpieces (NO. OF WORK))
(2) The items of report are scrolled right or left by pressing the "right" or "left" cursor key (1 item/
cursor key operation). Note that the MAIN PROGRAM is not shifted.
SECTION 2 MacMan MAIN SCREEN
Eeospkku2003
4345-E P-6
EIOSPKKU2003R01

Advertisement

Table of Contents
loading

This manual is also suitable for:

Osp-e10

Table of Contents