Electrical Operation - Emerson ASCO 7000 Series Operator's Manual

Automatic transfer switches h–design 600 through 1200 amps
Hide thumbs Also See for ASCO 7000 Series:
Table of Contents

Advertisement

observe
these lights
Figure 1-5. Standard controls and indicators.
3 – Electrical Operation
This procedure will check the electrical operation of the
Automatic Transfer Switch. See Figure 1–5.
Be sure to close the enclosure door
before proceeding to prevent personal injury
in case of electrical system fault.
Transfer Test
Both normal and emergency sources must be available
and the emergency source generator (if used) must be
capable of being started in this procedure.
Perform steps 1 through 5 at the right. Observe the status
lights.
Black square means light is on.
White square means light is off.
This completes the Functional Test of the ATS.
INSTALLATION
GREEN
RED
GREEN
RED
1---5
(continued)
operate
this switch
The Transfer Switch Connected
1
To Normal and Normal Source
Accepted lights should be on.
Turn and hold Transfer Control
switch clockwise to Transfer
Test until the engine starts
2
and runs (within 15 sec.).
Emergency Source Accepted
light should come on.
Transfer switch will operate to
the Emergency position after
Feature 2B time delay. The
3
Transfer Switch Connected To
Emergency light should come
on and Load Connected to Nor-
mal light goes off.
Transfer switch will operate
back to Normal position after
Feature 3A time delay. For im-
mediate retransfer turn Transfer
Control counterclockwise to
4
Retransfer Delay Bypass. The
Transfer Switch Connected To
Normal light should come on;
Transfer Switch Connected to
Emergency light should go off.
The engine–generator will stop
after the Feature 2E time delay
5
(unloaded running engine cool-
down). The Emergency Source
Accepted light should go off.