Installation

DRAIN CONNECTIONS

Follow these guidelines when installing drain lines to prevent
drain water from flowing back into the ice machine and
storage bin:
• Drain lines must have a 1.5 inch drop per 5 feet of run
(2.5 cm per meter), and must not create traps.
• The floor drain must be large enough to accommodate
drainage from all drains.
• Drain pump discharge line must terminate at an open site
drain.
• Maximum rise - 12 feet (3.7 m)
• Maximum run - 100 feet (30.5 m)
Approximate Height of Ice Machine Drain
Leg Levelers
Installation with Leg Option

WATER SUPPLY AND DRAIN LINE SIZING/CONNECTIONS

Location
Water
Temperature
Ice
40°F (4°C)
Making
Min.
Water
90°F (32°C)
Inlet
Max.
Ice
---
Making
Bin Drain
Drain
---
Pump
12
3" (76 mm)
7" (179 mm)
Water
Ice
Tubing Size
Pressure
Machine
Up To Ice
Fitting
Machine
Minimum
1/4"
20 psi
(6 mm)
(6 mm)
(138 kPA)
OD
Minimum
Outside
Maximum
Copper
80 psi (551
Tubing
Diameter
kPA)
---
3/4"
(19 mm)
(19 mm)
Hose Barb
Minimum
Diameter
---
3/8"
(9 mm)
(9 mm)
Hose
Minimum
Diameter

Step-by-Step Installation Procedure

1. Prepare the site by following the instructions under
Electrical Service and Water Supply and Drain
Requirements.
2. Remove ice machine from carton.
3. Inspect for damage.
4. Remove literature/warranty packet and drain hose from
inside the ice machine.
5. Adjust leg levelers (or install optional legs). Refer to
"Leveling The Ice Machine" on page 13
6. Reverse door if desired. See "Installation Checklist" on
page 14.
Fitting
7. For a gravity drain, install drain hose to drain on back of
1/4"
ice machine and route to open site drain. For optional
drain pump method, see "Drain Pump Option" on page
13.
3/4"
Inside
3/8"
8. Use compression fitting to connect the Water Inlet on
Inside
back of ice machine to the prepared 1/4" ID cold water
line. Refer to "Water Supply and Drain Requirements" on
page 11
9. Open the shut-off valve on the water line.
10. Connect electrical plug to grounded (three-prong),
polarized outlet. See "Electrical Service" on page 10
11. Place ice machine back in position and check for level
again. Make any necessary adjustments.
12. Prepare descaler and sanitizer solution and clean and
sanitize the ice machine according to steps 1 through 7
"In Place Cleaning/Sanitizing Procedure" on page 18.
13. Press Power button.