Version With Welding End; Heat Treatment Of Weldseams; Flap Indicator; Float Installation - Igema NA7-50 Installation And Operating Instruction

Magnetic level indicator
Table of Contents

Advertisement

7.2 Version with welding end

Respect installation position!
Remove protection caps from connection flanges. Caps only serve as transport
protection.
Assembly only by using welding process 111 (manual arc welding) and 141
(tungsten inert gas welding).
7.3 Heat treatment of weld seams
Supplementary temper tests of weld seams are not required.

7.4 Flap indicator

The centre of the lower process connection is the reference point for the zero mark of
the flap indicator (3).
The flap indicator fixed by bolt springs (3.1) with stop clamp (3.2) to the standpipe
(factory-made) can be turned into desired position.
Also turn stop clamp!

7.5 Float installation

The float (2.1) with inner magnetic system and the new gasket (2.2) are packed and
fixed outside of the standpipe (2) when the unit is supplied.
Open cover flange (2.3)
Carefully remove float packing
Insert float with top-heavy side upwards into standpipe (top-heavy side with colour
marking)
Tighten cover flange (2.3) and associated gaskets (2.2) with standpipe using
successively opposite diagonal tightening (see chapter 9.2)
Remove float before carrying out pressure test of boiler!
Float may remain in standpipe if there are valve between boiler and
Caution
standpipe which are closed during the test.

7.6 Drain piping

Check bolting drain valve (A) / standpipe (2) and retighten if necessary.
Mount drain piping on drain valve (A) (to be provided by the customer).
Ensure that drain piping has free outlet to atmosphere and is protected
from pressure peaks!
Caution
Close valves.
14