5. Starting with the nozzle control valve at the outer end of the boom, begin connecting the valve tee branches to
the nozzle control valves.
FIGURE 13. Securing Valve Branches
6. At each valve branch, adjust the cable as necessary to provide slack between nozzle control valve connections.
The large round connector on the secondary boom cable should reach to the mid-boom fold point after all
nozzle control valves are connected.
FIGURE 14. Primary and Secondary Boom Cable Connection at Mid-Boom Fold Point
7. Repeat step 1 through step 5 to route and connect the secondary boom cable on the opposite boom.
NOTE:
Route and connect the primary and secondary cables before securing the cable with the supplied zip
ties.