3.1 Installation Process

This topic describes the SmartLogger installation process.
The SmartLogger installation process is shown in
Figure 3-1 Installation flowchart
Table 3-1
Table 3-1 Description of the installation process
Step
1
2
3
4
Issue 04 (2013-12-15)
describes the installation process.
Operation
Checking Before
Installation
Preparing Tools
Determine the installation
position.
Installing the SmartLogger
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
3-1.
Description
Before unpacking, check that the outer packing
materials are intact. After unpacking, check that
deliverables are complete and intact.
Prepare tools required for installation and electrical
connections.
Before installing the SmartLogger, determine an
appropriate position to ensure that the
SmartLogger works properly.
The SmartLogger can be installed on a desk, a wall
or along a guide rail.
3 Installation
13