Nuova Simonelli prontobar Maintenance Plan

Nuova Simonelli prontobar Maintenance Plan

Hide thumbs Also See for prontobar:

Advertisement

Quick Links

Advertisement

loading

Summary of Contents for Nuova Simonelli prontobar

  • Page 2 Address: __________________________________________________________________ __________________________________________________________________________ Preventive Maintenance (PM) Schedule As recommended by Nuova Simonelli, PMs should be scheduled in 3 months intervals for super-automatics to keep the machine operating at the highest level as described in the Standard preventive Maintenance. The above installation company agrees to perform _____ PMs for every year.
  • Page 3: Installation Checklist

    INSTALLATION CHECKLIST Check if weight and dimensions are compatible with the installation location  (330x520x600mm WxDxH; 37Kg net weight)  Check if machine power is compatible with the installation location (Voltage: 220V, Frequency: 50Hz or 60Hz; Absorption 2400W  Check if the water pressure in the installation location is less then 4 bars (Direct Connection machine only) Connect the water inlet pipe (Direct Connection machine only) ...
  • Page 4 Check products and set Right grinder   Check products and set Left grinder ESPRESSO: delivery time (from pushing the button and the finish of brewing) must be set around 25–30s; COFFEE: delivery time (from pushing the button to the end of brewing) must be set around 30–35s;...
  • Page 5 Standard preventive Maintenance__________________________________ Maintenance periods Maintenance operations 3 months 6 months 1 year 12.500 25.000 50.000 cycles cycles cycles Run complete cleaning cycle Run decalcification program Disassemble and clean delivery nozzle Disassemble and clean milk frothing system (1 step only) Change the 3 gaskets in the milk foamer (1 step only) Clean or change if necessary the T plastic...
  • Page 6 Change upper and lower piston shower Change scoop cam driver Change scoop cam spring Lubricate the movement screw bearings with Nuova Simonelli silicon grease Lubricate with Teflon spray the guides bushes and the movement screw near the plastic nut Clean the movement guides Time requested (1) 3 months maintenance or 12.500 cycles is recommended...
  • Page 7 Supplementary preventive maintenance_ ___________________________ In the supplementary preventive maintenance, are not considered the electric and electronic component like Control board, display, grinder motors, pump motor and group motor, because is difficult to estimate the life cycle. Deadline Maintenance operations Every 2 years or - change the complete milk frother 100.000 cycles - change the complete air regulator...
  • Page 8 Pump pressure: Pump pressure: Supplementary maintenance: Supplementary maintenance Customer requests: Customer requests: Maintenance work done by: Maintenance work done by: Official Nuova Simonelli Official Nuova Simonelli dealer Stamp dealer Stamp Next maintenance: Next maintenance: 3 months □ 6 months □...
  • Page 9 Pump pressure: Pump pressure: Supplementary maintenance: Supplementary maintenance Customer requests: Customer requests: Maintenance work done by: Maintenance work done by: Official Nuova Simonelli Official Nuova Simonelli dealer Stamp dealer Stamp Next maintenance: Next maintenance: 3 months □ 6 months □...