• Mount curtain guides to the wall surface using supplied fasteners. See FIG 5A and 5B.
• Check "G" Dimension as illustrated in FIG 4 on page 5. "G" Dimension must match your "DOOR INSTALLATION DATA" sheet.
• Both guides MUST be on a level line and both guides MUST be plumb.
• The "G" Dimension must be held within 1/8" over the entire height of the guides.
• If using the Cremone cylinder lock tubular bottom bar you will need to include the standout tubes between the guides and the wall as shown in FIG 5C. The standout
tubes will need to be pre-drilled onsite to match the holes in your curtain guide.
WARNING
Follow instructions and use proper lifting equipment and correct lifting procedure to avoid serious injury or death.
WARNING
Rapidly closing curtain could result in death or serious injury. Do not remove factory binding around curtain assembly until step 3.
STEP 2
STEP 2
INSTALL HEAD ASSEMBLY
• Lift the head assembly using a fork lift or other appropriate lifting equipment and lower it onto the top of the guides, inserting the support bars into the guide as shown
in FIG 6.
• Be sure the support bars are fully inserted into the guides on both sides. See FIG 7
• Install the wall fasteners provided into the head plate flanges to attach it to the jamb. See FIG 7