Mounting Kits PR 6002
4

Installation

4.1

Before the Mounting

The foundation for the mounting kit must be horizontal (use spirit level), flat and rigid for the loads to
be supported.
The load must be distributed as symmetrical as possible in order not to partially overload the load cells.
The foundations of the mounting kits must be aligned and the supporting surfaces of the weighing
object (e.g. vessel) must mount in parallel.
If soft layers (e.g. from rubber or plastic) for vibration damping or for temperature insulation are
inserted between mounting kit and vessel and / or between mounting kit and supporting construction,
you must take care to insert between soft layer and mounting kit a load equalisation plate to ensure an
even load distribution on the mounting kit.
The version of insulation and equalization plates is application-dependent.
4.2

Tightening Torques

Insert a washer between bolt head and mounting kit. Suitable bolts and washers as well as the
recommended tightening torque are given in the table below.
Mounting kit
Bolt
DIN 4014 or DIN 4017
PR 6002/02S
PR 6002/03S
PR 6002/04S
PR 6002/05S
M12-A2-70
PR 6002/10S
PR 6002/11S
PR 6002/20S
PR 6002/21S
EN-18
Washer
DIN 7349
13 × 30 × 6 A2
Installation Manual
Tightening torque
70 Nm