FusionModule1000A20 Prefabricated All-in-One Data
Center
Maintenance Guide
Skill requirement: fire engineer
Procedure
Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant
control panel.
Step 2 Remove screws from the horn strobe cover using a Phillips screwdriver, and remove the
cover.
Figure 4-27 Removing the horn strobe cover
Step 3 Remove cables from the horn strobe.
Issue 01 (2019-07-15)
Before replacing the horn strobe, inform the related administrative departments of the
temporary downtime of the fire control system. After the replacement, inform the
administration department that the system has become operational.
Copyright © Huawei Technologies Co., Ltd.
4 Parts Replacement
61