Akd-8-Programmer Disconnects; Procedures - GE EntelliGuard AKR30S-800A Installation Manual

R3 & r6 type retrofill circuit breakers 800-5000a
Table of Contents

Advertisement

Tools needed: Philips Head screw driver, wire strippers, wire cutters.
AKD-8—Programmer Disconnects
The programmer disconnect consists of 2 assemblies, one mounted on the breaker side and the other
mounted on the cabinet. The breaker side assembly consists of the mounting bracket and plug assembly.
The compartment side assembly consists of the plug assembly mounted on a spring-loaded assembly that
receives the breaker.

Procedures

1. Identify the existing programmer disconnect assemblies in the compartment.
The existing programmer disconnect plugs used in AKD-8 generation of the AKR breakers are provided
on the left side for the AKR30/30H/50/50H/30L/T-50H/75/100/125 and on the Right side for the AKR30S
retrofits.
Programmer disconnects are provided with legacy AKR breakers in AKD-8 LVS. The breakers were
equipped with the following pin configurations, depending on the application:
9-pin configuration (Manual plug resulting from a trip unit conversion kit)
12-pin configuration ( Dash 1 breakers, 12 pin Tyco type plug ~ 1988-2015)
24-pin configuration ( Original MicroVersa Trip disconnect –AMP Rectangular plug.
EntelliGuard R Circuit Breaker Retrofill AKD-8 Installation Manual
38
WIRING
• Before installing the breaker, the
secondary disconnects must be wired
to the breaker.
• Wires with wire markers are provided
on the breaker. Make sure that the
switchgear wiring connection points
match up with the original wiring of the
cubicle. This ensures that all wiring
connections are properly made.
Wrong connections will cause the
breaker to malfunction.
WIRING
• Note: Look for the wiring connection
scheme on the existing or old terminal
block and use the same references or
wiring information while re-wiring the
new terminal block.