Installation
Installation of end box & Installation of the joint

Installation of end box

The reinforcement of the end tap box installed in riser maybe carried out referring to the Fig 2.9.
Fig. 2.9
Installation of the joint
The joint uses double-headed "break off" bolt. It has a intension tag which helps to notice the position.
Fig. 2.10
Make the two busway face to face, and put apart 40~50mm between them.
Insert the joint between the two busway, and screw down the bolt until the first cap be cutted and the tag drop. (The
standard torque is ≧62N.m )