Step 36
Install Upper 2x4 Gable Overhang
1. Install a 79-1/2" long 2x4 on the side of the dormer under the roof sheathing.
Use 10d coated sinker nails.
:
:
:
Step 37
Install Upper Gable Trim & Fascia Trim
1. Install an 80-1/2" long 1x6 dormer rafter trim flush with the top of the roof sheathing and
end of the rafters using 8d galvanized box nails spaced 16" apart. Trim to fit, if needed.
.
.
.
.
:
:
. .
. .
.
.
. .
.
2x4 Gable Overhang
4. Install 36-1/2" long 1x3 corner
trim on the side of the dormer
using 8d galvanized box nails.
5. Repeat steps to install 2x4 and
corner trim on the other corners.
2. Install (2) two 73" long fascia
boards across the rafters using
8d galvanized box nails. Trim
to fit as needed.
3. Repeat to install gable trim and
fascia on the opposite corner and
the back of the building.