Overview
This document is intended for Ensemble certified installation professionals who are
commissioning Ensemble systems in the field. The process is composed of two phases: Installer
Toolkit communications, and Functional Testing. This document outlines the steps necessary to
establish successful communication between Ensemble components. A separate tech brief,
called Ensemble Commissioning: Functional Testing outlines proper testing procedure.
Contents
Overview ................................................................................................................................ 1
Preparing for Installer Toolkit Communications ....................................................................... 1
Commissioning Instructions ................................................................................................... 2
Decommissioning an Encharge/Enpower While Replacing it On Site ....................................12
Preparing for Installer Toolkit Communications
The following process assumes all Ensemble equipment has been installed in a code compliant
manner, tested for appropriate voltages and are ready to be energized.
For all products, always follow the SAFETY INSTRUCTIONS and instructions in the Enphase
quick install guides and installation manuals.
DANGER! Risk of electric shock. When energizing equipment in step D, check that Encharge
units are properly wired as prompted. Miswiring can result in a safety hazard. Note that the
ground connection does not have a L1 or L2 connection as this introduces a safety hazard.
Ensemble is commissioned using Installer Toolkit. Ensure Installer Toolkit is updated to
version 3.X or later:
1
© 2020 Enphase Energy Inc. All rights reserved.
July 24, 2020

Advertisement

loading

Summary of Contents for enphase Ensemble

  • Page 1 Overview This document is intended for Ensemble certified installation professionals who are commissioning Ensemble systems in the field. The process is composed of two phases: Installer Toolkit communications, and Functional Testing. This document outlines the steps necessary to establish successful communication between Ensemble components. A separate tech brief, called Ensemble Commissioning: Functional Testing outlines proper testing procedure.
  • Page 2: Commissioning Instructions

    After commissioning is complete, phone can be reset to automatic sleep.  The Enphase Envoy must have software version 6.0.X or later for commissioning and operation. You can update the Envoy software using Installer Toolkit. ...
  • Page 3: Commissioning Process

    C. Installer Toolkit Step 2, Devices & Array: C.1. Enter the total count of each device type to be added in the system. © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...
  • Page 4 Ensemble Commissioning: Installer Toolkit Communications Manually scan the serial numbers of Ensemble components into Installer Toolkit. C.1.1. Enpower and Encharge serial numbers must be manually scanned, while PV microinverters can use power line scan. C.1.2. It is strongly recommended to manually scan the PV microinverters as a power line scan can “poach”...
  • Page 5 E.1.2. Selecting a ToU rate for Encharge batteries automatically sets the batteries to a savings mode. E.2. To complete functional testing, Enphase recommends selecting a single rate tariff during commissioning. Tariff and battery storage modes can be changed using the Enlighten Mobile app or the Enlighten Manger web interface post installation.
  • Page 6 F.9.6. If, after completing the previous step, the Envoy software version shown on the Update Firmware button does not match the Envoy software version © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...
  • Page 7 F.10. Tap Start Provisioning Devices at the bottom of the Envoy Connectivity screen. G. Installer Toolkit step 5, Provisioning Devices: G.1. You must be Ensemble training certified to provision Ensemble devices. If you are not, you will be asked to select a certified user from your company.
  • Page 8 H. Confirm that the Encharge batteries are communicating with the Envoy by checking Installer Toolkit step 2: Device & Array. Encharge batteries should display “communicating” as follows: © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...
  • Page 9 H.3.5. Power ON Enpower, that is, turn ON the utility-side breaker in Enpower or the supply breaker to Enpower in the main panel. © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...
  • Page 10 Encharge batteries are charging or discharging in the devices section of Installer Toolkit. K. Installer Toolkit step 7, Generate a Summary Report: © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...
  • Page 11 N.1. Functionality testing should be completed to ensure grid up, grid down, and transition states are behaving as expected. N.2. Refer to the Ensemble Commissioning: Functional Testing Tech Brief for a checklist of these steps. © 2020 Enphase Energy Inc. All rights reserved.
  • Page 12 3. Add and provision the new devices as documented steps C and G in the Error! Reference source not found. section. © 2020 Enphase Energy Inc. All rights reserved. July 24, 2020 ___________Installer Initials: All steps complete on this page...