Technical Specifications
Materials
Stainless Steel
Connections
1
"
2
Test pressure
5.2 Bar
Testing authority
EN442
Maximum operating pressure
4 Bar
Maximum working temperature
90 ºC
Packaging
Wrapped in polyester, in cardboard box with polystyrene
blocks
PLEASE NOTE: Systems using micro bore pipework must have adequate pressure and flow 
rates for the number and style of radiators on the system.
Terms & Conditions
All products must be inspected once removed from the packaging and The Radiator Company notified
within 28 days of delivery of any scratches, blemishes or other damage.
The Radiator Company will then replace the radiator.
Imperfect radiators should therefore not be fitted and The Radiator Company will not accept responsibility
for replacement of scratched or damaged radiators once they have been fitted. This includes any
consequential loss or cost of fitting.
If The Radiator Company are not notified within 28 days of the date on the signed delivery note then it
will be deemed that The Radiator Company have fully complied with its obligations and claims will not be
considered.
Failure to comply with any of the above may invalidate any claims.
We recommend that after you check the product on delivery that it is stored in its packaging to prevent
damage prior to installation. The Radiator Company cannot accept responsibility for items damaged after
delivery.
Guarantees & Liabilities
As we are not the manufacturers of this product we will take all reasonable endeavours to make over to
you the benefit of any warranty or guarantee given by the manufacturer, which is usually five years on most
of our range. (Copies of specific guarantees for any of our products are available on request).
The guarantees in all cases are subject to the products being installed in accordance with British and or
European standards as well as these fitting instructions. The guarantees in all cases are restricted to the
free of charge replacement or repair of the failed product only. Our liability will under no circumstances
extend beyond the repair or replacement of the product supplied by us. Claims for either labour in
replacement or damage to property are not admissible. Any goods that are returned, in the event of a
problem, will belong to The Radiator Company.
If you have any questions please contact us: 01342 302250, www.theradiatorcompany.co.uk
flow and return.
THE
RADIATOR
COMPANY
Fittings Instructions
LYNX_IR_1.0
A brand of
Lynx
Please read these instructions and terms and
conditions carefully prior to installation.
Failure to do so may invalidate the warranty
The Radiator Company
Units 13 - 14 Charlwoods Road
East Grinstead
West Sussex
RH19 2HU
, Italy's leading manufacturer of design led radiators
10

Advertisement

loading
Need help?

Need help?

Do you have a question about the THE RADIATOR COMPANY LYNX and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for IRSAP THE RADIATOR COMPANY LYNX

  • Page 1 Technical Specifications RADIATOR Lynx COMPANY Materials Stainless Steel Connections ” flow and return. Fittings Instructions Test pressure 5.2 Bar Testing authority EN442 Maximum operating pressure 4 Bar Maximum working temperature 90 ºC Packaging Wrapped in polyester, in cardboard box with polystyrene blocks PLEASE NOTE: Systems using micro bore pipework must have adequate pressure and flow ...
  • Page 2 Hang Radiator Diagrams of Lynx Pipe Centres Slide on the bracket sleeves over the Pipe centres left to right 430mm / width minus 70mm top two bracket studs on the back of the radiator. 55mm to 80mm Pipe centres from wall Lift the radiator in its final desired place Depth from wall 95mm to 120mm...