SUBMERSIBLE BATTERY INSTALLATION
Step 4: Install Bus Bars & BMS Wiring for 12 Volt Battery
Configuration
Lay the battery box (Horizontally) onto a
flat surface with the battery label faced up.
LEFT BUS BAR
TOP BUS BAR
Remove vertical (Left) bus bar and
associated battery terminal hardware from
included packaging. Slide ring terminal of
Red wire (labeled #1 extending from BMS)
RIGHT BUS BAR
over end of provided battery terminal bolt,
and through top hole of vertical bus bar.
NOTE: Proper placement of hardware is in
the following order - Bolt- head-split lock
TERMINAL
washer-flat washer-ring terminal-bus bar.
TERMINAL RED WIRE 1
TERMINAL RED WIRE 4
Install bolt/ring terminal/bus bar assembly into positive terminal of battery cell #1, and hand
tighten. Install remaining terminal bolt into bottom hole of vertical bus bar and into negative
terminal of battery #3.
Next, remove from packaging and install horizontal bus bar from negative terminal of battery #1
to positive terminal of battery #2 (repeat above process to ensure (Red) #2 wire from BMS is
installed to positive terminal of battery #2).
Install remaining vertical bus bar from negative terminal of battery #2 to positive terminal of
battery #4 (repeat above process to ensure (Red) #4 wire from BMS is installed to positive
terminal of battery #4).