PDU8000 Modular Integrated PDC V1.0
User Manual
Table 6-3 Cable installation checklist
No.
1
2
3
4
5
6
Before the power-on check, switch on all input and output circuit breakers to check for short
circuits. After ensuring that no short circuit occurs, switch off all input and output circuit
breakers.
Table 6-4 Electrical parameters checklist
No.
1
2
Issue 07 (2019-04-15)
Check Item
All bolts are tightened, especially the bolts used for
electrical connection. Flat washers and spring washers are
installed properly.
Cables are bundled neatly, and cable ties are secured evenly
and properly.
Cables are routed for ease of future maintenance and
expansion.
There are no unnecessary adhesive tape or cable ties on the
cables.
Exposed parts near the wiring terminals and lugs are
wrapped in PVC insulation tape or heat shrinking tubing.
The cable routing for power cables and monitoring cables
meets the requirements for routing power cables and signal
cables and complies with the cable routing plan.
Check Item
Use a multimeter to check that no short circuit occurs
between any two phases of L1, L2, L3, N, and PE on the
AC input side.
The AC input voltage is within the rated voltage range.
Copyright © Huawei Technologies Co., Ltd.
6 Power-On Commissioning
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
Result
□Yes □No
□Yes □No
50