VERITAS 5U84 Hardware Service Procedure

Replacing a fibre channel sfp module in storage shelf

Advertisement

Veritas Appliance
Hardware Service Procedure
Replacing a fibre channel SFP module in a Veritas 5U84 Storage
Shelf
Document Number: 218
Version: 1.0 (11/06/17)
Purpose
This document describes the process for replacing a fibre channel SFP module in a 5U84 Storage
Shelf that is connected to a 5340 appliance.
Electrical Safety
The static discharged by human bodies can damage static-sensitive components on the boards.
When installing and maintaining the equipment, observe appropriate electrostatic safety precautions
to prevent personnel injuries or device damage.
When operating a device in an electrostatic sensitive area, you must take electrostatic-discharge
(ESD)-preventive measures. These include wearing ESD-preventive gloves, an ESD-preventive wrist
strap, and ESD-preventive clothes to avoid personnel injury or device damage.
To prevent damage to the device, pay attention to the following during operations:
Do not touch devices with bare hands because ESD from the human body may damage the
electrostatically sensitive elements on a board.
When dealing with the server or any of the internal components, wear an ESD-preventive wrist
strap, ESD-preventive gloves, and ESD-preventive suit.
High availability (HA) appliance service considerations
Attention: A HA or multi-node appliance is serviced in the same manner as a single node appliance.
About replacing a Fibre Channel SFP module in a 5U84 Primary
Storage Shelf RAID Controller
The 5U84 Primary Storage Shelf uses two RAID Controllers located in the top two slots of the shelf's
back panel. Each RAID Controller holds four SFP modules that can be individually replaced.
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 5U84 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for VERITAS 5U84

  • Page 1 About replacing a Fibre Channel SFP module in a 5U84 Primary Storage Shelf RAID Controller The 5U84 Primary Storage Shelf uses two RAID Controllers located in the top two slots of the shelf's back panel. Each RAID Controller holds four SFP modules that can be individually replaced.
  • Page 2 HSP 218 - Replacing a Fibre Channel SFP module Requirements Use the following to verify the requirements of the service. Verify you have the following items Replacement SFP module ESD wrist strap Removable labels to mark the fibre optic cables Removing a faulty Fibre Channel SFP module Use the following procedure to remove a faulty Fibre Channel SFP module.
  • Page 3 HSP 218 - Replacing a Fibre Channel SFP module Disconnect the fiber optic cable by depressing the clip located at the top of the fiber optic cable connector and then pulling the connector out of the optical module. (Optionally) If available, place the fiber cable plastic guards into the opening of the fiber optic cable tubes.
  • Page 4 Remove the plastic guards from the ends of the fiber optic cable tubes. Insert the connector into the SFP module until the connector clicks Remove the temporary label from the fibre optic cable. Verify that the system is functioning properly. If it is not, contact Veritas Technical Support.

Table of Contents