1MRK 514 016-UUS B
5.3.2
Arranging ventilation
Ventholes are located at the bottom and on the back plate of the IED. Reserve sufficient space
round the IED to ensure adequate ventilation.
•
Reserve at least 2U below and above the unit.
•
Reserve for rack mount approximately 10 cm behind the unit, measured from the surface of
the cover.
•
Ensure sufficient space for the wiring and the installation of cable ducts.
650 series
Installation manual
Check the allowed minimum bending radius from the optical cable manufacturer.
© Copyright 2013 ABB. All rights reserved
Section 5
Mounting
GUID-9E1949A6-180D-4626-9784-C06A9A65FE89 v2
19