Raising The Crossbeams; Runway Installation; Cylinder And Cable Installation - Titan HD4P-12000 Installation, Operation & Maintenance Manual

4-post lift
Table of Contents

Advertisement

RAISING THE CROSSBEAMS

4) Raise the crossbeams until the primary safety locks engage to facilitate Cable routing
and final assembly.
5) The COLUMNS and CROSSBEAMS will now be in position and spaced properly for the
runways. Be careful not to disturb the Columns and Crossbeams at this time as they
may tip over causing personal injury or harm.

RUNWAY INSTALLATION

6) Position the POWERSIDE RUNWAY on top of the Crossbeams with the UTILITY RAIL
towards the center. The fitting holes located at the side of the Powerside Runway
should be adjacent the POWER UNIT COLUMN. Align the holes in the runway with the
holes on the Crossbeams and bolt together (torque to 35-45 PSI) using hex head bolts
and nuts. (Refer to Fig. B) Complete the same process for the offside runway.

CYLINDER AND CABLE INSTALLATION

7) Locate the POWERSIDE RUNWAY easily identified by the Cylinder and Sheave
roller mounting structures welded on the underside. The Powerside Runway will be
positioned on the left of the lift where the Power Unit is installed.
8) In order to install the cables, it is necessary to first extend the HYDRAULIC CYLINDER.
Install Cylinder and Cables as shown in Fig. C.
Steel Cable
Fig. B
10
Bolt runway to the
crossbeams using hex
head bolts and nuts.
Cable
Block

Advertisement

Table of Contents
loading

Table of Contents