7. Start up of the BMT 2000 Hotmelt Machine

• Plug the machine in to a 220 – 240V 50Hz power supply.
• Switch on the main switch. Tank, Pump, Hose, Gun, Temperature Control
will read the temperatures of their respective zones.
• A BMT 2000 will take approximately 2 hours (Refer to table on Page
17 to 19) to reach 185 - 190°C depending on ambient temperature.
• The machine will not run until all temperatures are above 165°C.
• Turn the Pot Knob halfway, or to the speed desired.
• Pull the trigger on the Gun to extrude Hotmelt. NEVER POINT THE GUN AT
ANOTHER PERSON!

8. To stop the Machine

• Place the Gun and Hose in a safe position.
• Switch off the Isolator.
99 Spring Road, Tyseley, Birmingham, United Kingdom, B11 3DJ
BASSRA MACHINE TOOLS LTD.
Tel: 0044 (0) 121 707 4343 / Fax: 0044 (0) 121 707 3535
Website: www. bassra.com / Email: sales@bassra.com

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bmt 1000Bmt 3000Bmt 4000

Table of Contents